Memorandum

City of Lawrence

Public Works

 

TO:

David Corliss, City Manager

Cynthia Wagner, Assistant City Manager

Diane Stoddard, Assistant City Manager

FROM:

Matt Bond, Stormwater Engineer/Farmland Project Manager

CC:

Charles Soules, Public Works Director

Date:

April 18, 2012

RE:

April 24, 2012 Agenda Item

 

Please include the following item on the City Commission Consent Agenda for consideration at the April 24, 2012 meeting.

 

Approval of final Change Order for the Demolition at the former Farmland Industries Site.  This is the final demolition contract change order covering all outstanding items.  The total change order amount is $11,552.92.

 

Project History.  On September 29, 2009 the City closed on the ownership of the former Farmland Industries Nitrogen Plant Site at no cost to the City. This site was acquired to help with the remediation of the site and to facilitate the development of the site and corresponding job growth. In preparation of site development the existing building structures, piping and corresponding appurtenances needed to be demolished. The City Commission authorized staff to distribute a request for proposals for demolition services on the property on September 28, 2010

 

On December 21, 2010 the Lawrence City Commission approved awarding the Demolition Services (Project No. PW1015) contract to R.D. Johnson Excavating in the amount of $252,000.

 

Project Status.  Demolition activities on site have been completed.  Master Planning for the redevelopment of the project are underway. The Final Draft of the Remedial Design/Remedial Action Plan will be submitted to the Kansas Department of Health and Environment on April 20th.

 

Change Order Details.  During the demolition it was discovered that there was a considerable amount of residuals in the various small storage tanks on site.  These tanks needed to be rinsed out and the corresponding waste product produced needed to be disposed of properly.  The following items are included within the final Change Order.

 

  • Inspection of all small storage tanks on site
  • Cleaning of all small storage tanks on site
  • Shoring of onsite Power Poles - necessary for power to remediation pumps
  • Removal of Bulbs & Ballasts in Administration Building
  • Removal of Bulbs & Ballasts throughout plant site
  • Tank disposal

 

Exhibit A of the demolition contract states:  After the first 1500 tons of steel is recylced the proceeds for recyclable steel will be split between the contractor R.D. Johnson and the City of Lawrence.  The split will be as follows:  75% R.D. Johnson and 25% for the City of Lawrence."  There was a total of 1798.48 tons of steel recycled with the demolition of the plant.  This correlated to a credit of $13,431,60 back to the City as its share of the recycling.  The City was also able to take advantage of a cost savings by using its hazardous household waste contract with the State in the disposal of the following tabulated items:

Mercury Bulbs

101

4' Fluorescent Bulbs

435

8' Fluorescent Bulbs

187

Ballast PCB

89

Ballast Non-PCB

306

 

 

 

 

 

 

This not only saved the City in disposal fees but keeps these products out of the landfill.

 

Project Funding.  The project was paid for out of Capital Improvement Reserve Funds and the remediation funds transferred to the City upon acquisition of the property.  The change order costs will be financed with remediation fund money.

 

COSTS

 

Original Contract

$252,000.00

First Change Order (remove tertiary treatment basin)

$3,000.00

Final Change Order

$11,552.92

Total Project Cost

$266,552.92

 

 

 

 

 

 

Action Requested.  Public Works staff requests approval of final Change Order in the amount of $11,552.92.

 

Attachments.  Pictures

 

Respectfully Submitted,

Matt Bond, P.E.

Matt Bond, P.E.

Stormwater Engineer/Farmland Project Manager